Sl No. Particulars of the proposal Type  NOC/New/Additional R.R No. Existing contract Demand in KVA Requisitioned load in KVA Total load in KVA Date of receipt of proposal at Corporate office Date of forwarding of proposal to KPTCL for its concurrence Date of receipt of concurrence from KPTCL Date of communicating approval to the Zonal Chief Engineer of BESCOM  Remarks if any
1 Arranging HT power supply to an extent of 1250 KVA  in favour of M/s UMBELL Properties Pvt. Limited, Golf link Park, Challaghatta village, Murugeshapalya, Koramangala, Innerring road Bangalore Bangalore. NEW __ __ 1250 1250 29-02-2012 6908-09                       dated 19-03-2012 Yet to be received     
2 Electrification of residential Layout  of M/s KNS Infrastructure Pvt. Limited at  different sy.No. in Donnenahalli village and different sy nos of Byalahalli village, Tavarekere  Hobli, Magadi subdivision. NEW __ __ 2599KW             3057 KVA) 2599KW (3057 KVA) 16-09-2011 4693-94 dated           13-01-2012 Yet to be received     
3 Issue of NOC  for arranging power supply to an extent of 3222KW  to the proposed  MS building in favour of M/s Janadhar Constructions Pvt. Limited, at Medihalli village, Chandapura Subdivision. NOC __ __ 3222KW (3790KVA) 3222KW (3790KVA) 24-10-2011 3038-39 dated                  17-011-2011 Yet to be received     
4 Issue of NOC  for arranging LT power supply to an extent of 2237 KW  to the proposed  Residential apartment in favour of M/s Nitesh Urban Development Private Limited(GPA), Sri. B.C. Narayana Reddy, Sy No. 18/1c, Kaikadanahalli village Varthur Hobli, Bangalore in S-11 Subdivision.  NOC __ __ 2237KW                (2632 KVA) 2237KW                (2632 KVA) 12/1/2012 4859-60 dated                  25-01-2012 Yet to be received     
5 Arranging additional  power supply to an extent of 4550 KVA on EHT basis  on the existing R.R.No. KPUHT-56(having contract demand of 400KVA on HT basis) in favour of M/s Orchid Laminates Private Limited at Plot no. 298 Phase 2nd KIADB  Industrial area, Kanakapura subdivision, Ramanagara Division. Additional KPUHT-56 400 4500 4950 28-12-2011 4551-52 dated  30-12-2011 Yet to be received     
6 Issuing of NOC to  the proposed commercial building to an extent of 1484 KVA in favour of M/s Mind Tree Private Limited, at plot No.150, EPIP Layout, Whitefield, Bangalore pertaining to Indiranagara Division. NOC __ __ 1484 1484 30-11-2011 4161- 62 dated                         07-12-2011 Yet to be received     
7 Issuing of NOC to  the proposed commercial building to an extent of 7370 KVA in favour of M/s Irfan Razaq(GPA), Falcon House, different sy. Nosat Outer ring road, Kadubeesanahalli, No.1, Main guard cross Bangalore, in S-7 subdivision. NOC __ __ 7370KVA 7370 KVA 14-03-2012 6938-39                              dated    22-03-2012 Yet to be received     
8 Electrification of residential Layout  to an extent of 1890-5 KVA(2224KVA)  of M/s Kshemea Residency  at  different sy.No. in Attibele village ain chandapura Subdivision  NEW __ __ 1890.5KW(2224KVA) 1890.5KW (2224KVA) 19-03-2012 6940-41                              dated 22-03-2011 Yet to be received     
9 Arranging additional power supply to an extent of 5000KVA on the exiting R.R.No. CDPHT-266( which is having sanctioned load of 10000KVA) totaling to 15000KVA in favour of M/s Biocon Limited, at Jigani Bommasandra Link Road in Chandapura subdivision. Additional CDPHT-266 10000 5000 150000 1/3/2012 6609-10 dated              5-03-2011 Yet to be received     
10 Issuing of NOC  for arranging power supply to an extent of 19312 KVA in favour of M/s Coremind Software & Services Private Limited at Difft Sy Nos of Agara village in Begur Hobli, Bangalore in S-11 subdivision. NOC __ __ 19312 19312 17-12-2011 4400-01                                 dated 21-12-2011 Yet to be received     
11 Arranging HT power supply to an extent of 3500 KVA  in favour of M/s Venkateshwara Developers, Kamalaya  Hi soft, Sy.No, 21,22,27 & 28, Hosur Main road, Electronic city, Phase-2, Bangalore in S-8 subdivision pertaining to HSR Division. NEW __ __ 3500 3500 14-03-2012 6919-20                                 dated 20-03-2012 Yet to be received     
12 Issuing of NOC  for arranging power supply to an extent of3092KW(3638KVA)  for the proposed MS building (Residential Apartment) in favour of M/s DLF homes Rajapura Private Limited at Different Sy Nos of Rajapura village in Anekal Subdivision New __ __ 3092KW(3638 KVA) 3092KW(3638 KVA) 23-02-2011 6634-35                        dated 06-03-2012 Yet to be received     
13 Electrification of Residential layout for arranging power supply to an extent of 2575KW(3029KVA) in favour of Kotaguru Brahman & others, at  different sy Nos in Doddanagade village in Aneakal subdivision NEW __ __ 2575KW(3029KVA) 2575KW (3029KVA) 17-03-2012 6917-18                         dated 20-03-2012 Yet to be received     
14 Arranging additional  power supply to an extent of 3750 KVA on the existing HT installation bearing RR No. CDPHT-379 (with contract demand of 1250K VA  in favour of M/s Apotex Research Pvt. Limited at BIA, Plot No.2, 4th Phase, Jigani Link Road, Chandapura Subdivision. Additional  CDPHT-379 1250 3750 5000 27-02-2012 6479-80                         dated 01-03-2012 Yet to be recieved     
15 Arranging LT power supply to an extent of 1683KW(1980KVA) to the residential apartment(MS Building) Phase-2 in favour of M/s  Patel Engineering Limited, "Neo Town", Maragondanahalli village, Chandapura, Bangalore pertaining to Chanapura Subdivision New __ __ 1683 KW                  ( 1980KVA) 1683 KW                  ( 1980KVA) 3/3/2012 6637-38 dated               06-03-2012 Yet to be recieved     
16 Arranging LT power supply to an extent of 2280 KW(2682KVA) to the residential apartment(MS Building) in favour of M/s  SPL  Realtors Pvt. Limited, Sy No. 24 & 25 P, Mallasandra village in Bangalore New __ __ 2280KW (2682KVA) 2280KW (2682KVA) 13-03-2012 6775-76 dated              15-03-2012      
17 Electrification of residential layout for arranging power supply to an extent of  2200KW(2588KVA) in favour of Sri. Shetty Vengopal at Sy No. 301/1,301/2,302/1,303,304/1 and others in Jigani Village in Jigani section pertaining to Anekal subdivision New __ __ 2200KW (2588KVA) 2200KW (2588KVA) 8/11/2011 4007-09                  dated 21-1-2011      
18 Arranging Additonal Power supply on LT basis to MS building to an extent of 1361 KWs for the additionally constructed 4 wings (existing load of 791 KWs form the existing Shobha saffron block and Shobha Cinnemon wing-1) is totalling to 2152 KWs(2531 KVA) in favour of M/s Shobha Developers Limited" Shobha Cinnemon" at Sy. No. 86/2,88/1,88/3,89,90/1,90/2, Kudlu village Sarjapura Road, Bangalore pertaining to S-8 Subdivision  Additional __ 791 KW 1361KW 2152KW (2531 KVA) 11/1/2012 4737-38 dated               16-01-2012      
19 Arranging HT power supply to an extent of 2500KVA in favour of M/s Sabic Research & Technologies Pvt. Limited,  at Sy,No. 83/2,83/3 & 84/4, Chikkabommsandra Village pertaining to Chandapura Subdivision. New __ __ 2500 2501 31-10-2011 2979-80 dated               15-11-2011 11/1/2012 4686-87 dated 12-01-2012  
20 Arranging HT power supply to an extent of 2600KVA in favour of M/s Nitesh Residency Hotel Private Limited, No.99, Residency Road, Bangalore pertaning to E-3 Subdivision. New __ __ 2600 2600 27-06-2011 1839-40 dated 02-07-2011 12/9/2011 3333-34 dated 15-09-2011  
21 Electrification of Residential layout  in favour of M/s Soubhagya Properties  for arranging power supply to an extent of 2166KWs(2548KVA) at Sy.No. 5,8,9,10,15/1,15/2,15/3,15/4,16/1,16/3,17 of Huskur village and Sy.No. 40,42 of bendiganahalli village pertaining to Hoskote Subdivision. New __ __ 2166KWs (2548KVA) 2166KWs (2548KVA) 3/12/2011 4260-61 dated 14-12-2011 16-03-2012 6921-22 dated                20-03-2012  
22 1.Proposal for electrification of residential layout for arranging power to an extent of 2967KVA  in favour of Sri. Priya Krishna(GPA Holder) Sy.No.153/6,7,8,10,11,13,14,15,  Tavarekere village, Tavarekere Subdivision,  pertaining to  Nelamangala division.
2. Proposal for electrification of residential layout for arranging power to an extent of 2488KVA  in favour of Sri. Priya Krishna(GPA Holder) Sy.No.124/1,124/2,125/1,125/2, 154/2, 154/3, 154/3,154/3, 154/10,154/19 of Tavarekere village, Tavarekere Subdivision,  pertaining to  Nelamangala division
NEW __ __ 2522KW(2967KVA) 2081KW(2448KVA) 2522KW(2967KVA) 2081KW(2448KVA) 24-02-2012 6398-99 dated 29-02-2012      
23 Proposal for electrification of residential layout of Sri Pradeep Krishnappa(GPA Holder), for arranging LT power supply to an extent of 1888KW(2221kVA) at Sy.No.1P, 2P, 4P, 117P, 120P, 121P, 145P, 146P, 148P, Ajjanahalli Village, pertaining to Magadi Sub-Division NEW __ __ 1888KW( 2221KVA) 1888KW( 2221KVA) 24-02-2012 6400-01 dated 29-02-2012      
24 Proposal for electrification of residential layout of Sri Priya Krishna(GPA Holder), for arranging LT power supply to an extent of 2104KW(2475kVA) at Sy.No.12p,13p,51p, 52 muddayyanaplaya village Magadi Subdivision  NEW __ __ 2104KW (2475KVA) 2104KW (2475KVA) 24-02-2012 6402-03                  dated                  29-02-2012      
25 Issue of NOC for arranging EHT power supply to an extent of 19500kVA to the proposed M.S. Building (Commercial)   in favour of M/s Kalyani Tech Park Pvt. Ltd., Sy.No.15/1B, 23/2, 23/1, 14/P7, 14, 24/1, 26/1, 24/2, 26/2, 27, 23/1, 25/1, 25/2, 23/2, Kadubeesanahalli, Kariammana Agrahara Village, Varthur Hobli, Bangalore in S-7 sub-division pertaining to Koramangala division.  NOC __ __ 19500 19500 15-12-2011 4463-64                  dated 22-12-2011      
26 Arranging additional HT power supply to an extent of 2000kVA on the RR No. S11HT-25 (with CD of 1950kVA totalling to 3950kVA) in   favour of Sri Venkataswamy & Others, Developers, M/s Soul Space Projects Limited, Sy.No.89/6,78/7 & 78/8, Bellandur Village, Varthur Hobli, Bangalore pertaining to S-11 sub-division, HSR division, South Circle.  Additional S11HT-25 1950 2000 3950 14-12-2011 4329-30 dated           17-12-2011      
27 Proposal for arranging additional power supply  to an extent of 1000 kVA on the  existing R.R.No.S7HT-148 (with sanctioned load of  1900 kVA) totaling to 2900 kVA in favour of M/s RGA software System Pvt. Ltd., at No.64/4D, Outer Ring Road, Devarabeesanahalli, Bangalore pertaining to S-7 Subdivision, Koramangala division. Additional S7HT-108 1900 1000 2900 7/10/2011 2789-90 dated              03-11-2011      
28 Arranging LT power supply to an extent of 4129kVA(3510KW) residential layout of M/s Ramky Estates & Farms Pvt. Ltd., at Vajrahalli, in Nelamangala sub-division. NEW __ __ 3510KW                  (4129 KVA) 3510KW                  (4129 KVA) 16-01-2012 5586-87 dated               03-02-2012      
29 Arranging HT power supply to an extent of 950kVA in favour of M/s Adarsh Prime Projects Pvt. Ltd., No.20/3, Outer Ring Road, Devarabeesanahalli, Marathalli, Bangalore in S-7 sub-division pertaining to Koramangala Division.  NEW __ __ 950 950 25-01-2012 5586-87 dated              31-01-2012      
30 Proposal for arranging additional power supply  to an extent of 1000 kVA on the  existing R.R.No.AKLHT-76(with sanctioned load of  3000 kVA) totaling to 4000kVA in favour of M/s Hikel Limited, No.82/A, Jigani Industrial Area, Anekal Taluk, Bangalore Additional AKLHT-76 3000 1000 4000 27-08-2011 2164-65                           dated 17-09-2011      
31 Proposal for arranging additional HT power supply  to an extent of 750 kVA on existing the R.RNo.CDPHT-210(with sanctioned load of  2000 kVA), totaling to 2750 kVA in favour of M/s Geo Rock Forge Pvt.Ltd., at No.143/B, Bommasandra Industrial Area, pertaining to Chandapura sub-division. Additional CDPHT-210 2000 1000 3000 16-09-2011 2444-45 dated            30-09-2011      
32 Arranging LT power supply to an extent of 2300KW(2705kVA) for electrification of residential Layout of M/s Karnataka Housing Board, at Sy. No. 25,26,24/1,31/1,5,24/2, 22/1,6,7/1, 7/2,40, 37/2,36/3, 36/4 of Pattiganahalli Village and Sy. No. 89  and 90/1 of Korandahalli village Malur Talulk, Kolar District, pertaining to Malur subdivision.  NEW __ __ 2300KW   (2705KVA) 2300KW   (2705KVA) 23-09-2011 2442-43                  dated 30-09-2011 27-01-2011    
33 Issue of NOC  for the proposed commercial complex  in favour of M/s Reliance Prolific Traders Pvt. Limited at Mysore Road, Kengeri Hobli, Bangalore. NOC __ __ 4320 4321 29-02-2012  6570-71 dated           05-03-2012       
34 Arranging additional load to an  extent of  900KVA   on the existing EHT installation bearing R.R.No. KMMHT-3(with existing sanctioned load of 3100KVA) totalling to 4000KVA in fvour of M/s Madras Cement Limited, matthod in Hosadurga Subdivision. Additional MMHT-3 3100 900 4000 22-02-2012 6280-81                  dated 25-02-2012      
35 Arranging EHT power supply to an extent of 1000KVA in favour of M/s Banaglore Metro Rail Project at 1st Stage, peenya Industrial area, Bangalore NEW __ __ 1000 1000 18-02-2012 6278-79                   dated 25-02-2012      
RECRUITMENT in BESCOM
Date : Monday, September 25th, 2017
Power Interruption Information
Date : Monday, January 16th, 2017

Welcome to
HT Online Application

(New Initiative of BESCOM)

Know More